Electrical rough-in inspection checklist

An electrical rough-in inspection checks the wiring before walls and ceilings are covered: boxes, cable and conduit, circuits, grounding and labeling. Walk this checklist yourself before the inspector does. Each item gets Pass, Fail or N/A, and the electrician, the GC and the inspector sign off at the end.

Use it free on your phone
Free checklist from SRENE.io · myBivy for Trades

Electrical rough-in

Before the rough-in inspection and before cover.

JobArea / floorDateChecked by
BoxesPASSFAILN/A
Box heights and locations per plans
Box fill within limits
Boxes secured and flush to finish
Fire-rated walls: putty pads where required
Conduit & cablePASSFAILN/A
Conduit sleeves and penetrations
Connections, mounting and routing
Cable stapled/supported within 12 in. of boxes
Nail plates where within 1-1/4 in. of stud face
Firestopping / caulking at penetrations
CircuitsPASSFAILN/A
Circuits match panel schedule
Home runs labeled
AFCI / GFCI locations identified
Grounding and bonding in place
Code & identificationPASSFAILN/A
Identification / labeling
Code compliance (NEC and local amendments)
Smoke / CO locations per plans
Notes
Electrician (QC)NameSignatureDate
GCNameSignatureDate
Electrical inspectorNameSignatureDate

Run this checklist free on your phone, with photos and signatures: myBivy for Trades at srene.io. A field checklist, not the code; follow the code and amendments your jurisdiction has adopted.

What gets missed most

  • Missing nail plates where cable runs close to the face of a stud.
  • Cable not stapled or supported near boxes.
  • Overfilled boxes, or boxes that won't sit flush with the finished wall.
  • Home runs not labeled, so nobody can match circuits to the panel schedule.

This is a field checklist, not the code. Your inspector enforces the code and local amendments your jurisdiction has adopted.

Questions trades ask

When does the electrical rough-in inspection happen?

After the wiring, boxes and panel rough are in, and before insulation and drywall cover anything. The inspector has to see the work while it's still open.

What fails an electrical rough-in inspection?

Most often the basics: missing nail plates, unsupported cable, box fill over the limit, missing grounding or bonding, and work that doesn't match the plans. Walking a checklist first catches most of them.

Is this checklist the electrical code?

No. It's a field checklist. Your inspector enforces the NEC edition and local amendments your jurisdiction has adopted, so check those for exact requirements.

Can I use this checklist on my phone?

Yes. It's built into myBivy for Trades, free for up to 5 people: Pass, Fail or N/A on each item, notes, photos and readings, signatures on site, and a clean PDF for the GC.

Free for trade contractors

Pass the first inspection.

This checklist is built into myBivy for Trades: Pass, Fail or N/A on every item, notes, photos and readings, the GC signs on site, and a clean PDF goes out the same day. Free for up to 5 people.

The inspection checklist app · All free trade checklists · Free field forms